Line 11: Line 11:
 You are able to access each of the documents provided by selecting the blue text. The report/​document(s) will be downloaded for your review. You are able to access each of the documents provided by selecting the blue text. The report/​document(s) will be downloaded for your review.
 {{::​technical_inspection_documents.png|}} {{::​technical_inspection_documents.png|}}
 +==== Next Status ====
 The claim returns to the status it was in prior to the technical inspection request. The claim returns to the status it was in prior to the technical inspection request.
 +
 +When the claim has had an eligibility/​arbitration/​award decision made prior to the inspection, but as the arbitrator, you need to submit a new decision. Inform the PA, they will push the status back to awaiting [[eligibility hearing scheduled|eligibility]],​ [[arbitration hearing scheduled|arbitration]],​ [[award hearing scheduled|award]] decision. This will enable you to upload an additional decision or update the old decision. The PA will then remove the old decision from the system.
 +
 ====== Technical Inspection Review Overdue===== ====== Technical Inspection Review Overdue=====
 This is not so much as a decision, but that the arbitrator must view the report and comments if available from the consumer and manufacturer. Making the PA aware that they have this completed within __**10**__ days of **Technical Inspection Review Complete**. This is not so much as a decision, but that the arbitrator must view the report and comments if available from the consumer and manufacturer. Making the PA aware that they have this completed within __**10**__ days of **Technical Inspection Review Complete**.
 +==== Letter(s) ====
 +
 +  * An automated letter will be sent to the arbitrator reminding them that they must confirm that they have reviewed the technical inspection documents and forward their award.
 +
 +
  